Our Projects

Aeolian Dynamics Wind Farm - Larnaca, Cyprus

Aeolian Dynamics Wind Farm

TP Aeolian Dynamics Ltd (“TPAD”) was awarded a 10.8MW license in 2010 for developing Aeolian Dynamics Wind Farm (Agia Anna) in the area of Agia Anna village, in the district of Larnaca. Our wind farm layout comprises six Vestas V100 – 1.8MW wind turbines with a total wind farm capacity of 10.8MW.

TPAD has managed every aspect of the development of the wind farm. From the initial planning applications and wind studies through to the selection of designers, specification of the design brief, contract negotiation with contractors and on-site contract management.

Aeolian Dynamics Wind Farm Timeline

November 2005

Company Incorporation

November 2005
July 2006

Award of a Construction and Operation Permit from Cyprus Energy Regulatory Authority (CERA)

July 2006
October 2008

Environmental Approval from the Department of Environment

October 2008
August 2010

Project land secured with a Land Lease Agreement with the Ministry of Interior for 33 Years

August 2010
September 2010

Town & Planning Approval for a 10.8MW Wind Farm

September 2010
November 2010

Building Permit for a 10.8MW Wind Farm

November 2010
December 2010

Grid Connection Agreement with Transmission System Operator Cyprus (TSOC)

December 2010
December 2010

Power Purchase Agreement with Electricity Authority of Cyprus (EAC) for 20 Years

December 2010
December 2010

Subsidy Contract with RES Fund Management Committee

December 2010
April 2011

The wind farm broke ground with crane pads formation, road network and necessary earthworks

April 2011
2011 - 2013

Cyprus severe banking crisis caused significant delays and prevented the company from raising the necessary debt financing required for the completion of the project

2011 - 2013
October 2013

Successfully partnered with likeminded TFC Investment Management (“TFC”) to complete the necessary funding by raising a mixture of equity and debt financing

October 2013
June 2014

Completion of all required contracts for the wind turbines supply, civil and electrical works, allowing to recommence on time the wind farm construction

June 2014
February 2015

One month ahead of schedule commencing energy generation from the first completed wind turbine generators

February 2015
20th April 2015

Project commissioning successful completion and official commercial operation

20th April 2015
To – date

Maximizing Aeolian Dynamics wind farm financial and production efficiency and ensuring our wind turbines fleet optimization

To – date